Project Description

OWNER/OCCUPANT:  John Hopkins University

GENERAL CONTRACTOR:  Manhattan Construction

CLIENT:  JCM Associates

DESCRIPTION: The Johns Hopkins University Applied Physics Lab Building 30 is a 45,000-square-foot space science laboratory project that includes 6,500 square feet of ISO 7 cleanrooms and 6,000 square feet of ISO 8 cleanrooms. One of the ISO 7 cleanrooms includes a high-bay area with 2,600 square feet of floor space and a 40-foot clear hook height to a 10-ton bridge crane. Adjacent to that space is a high-bay ISO 8 cleanroom. This project is LEED®-registered with a certification goal of LEED Silver.

GSF/OSF:  45,000 square feet

SPECIAL FEATURES:  The 45,000 square-foot structure includes optics laboratories, mechanical assembly areas and a 60 foot high-bay clean room area capable of supporting both classified or unclassified integration and test operations.

CONSTRUCTION TYPE:  New Construction

CONTRACTORS SCOPE:  HVAC Sheet Metal Fabrication and Installation

DATE OF AWARD:  05/2011

COST AT AWARD:  $742,000

SCHEDULED COMPLETION TIME:  12 Months

CONTRACT TYPE:  Fixed Price

DATE OF COMPLETION:  09/2012

ACTUAL COMPLETION TIME:  13 Months